More than 60 companies have received 68 turnkey photovoltaic power plants delivered by E.ON Energie Romania, with an annual energy production of 1,400 MWh and investments of over 11 million euros, informs the energy supplier in a press release sent to Agerpres.
The number of projects implemented by September is almost double compared to the whole of last year, adds E.ON.
The 68 turnkey photovoltaic plants completed and delivered for more than 60 partner companies were designed to meet the specific needs and requirements of each partner and provide between 34 percent and 100 percent of their energy needs.
The construction of the systems involved the installation of over 34,000 photovoltaic modules in the locations of E.ON partners throughout the country, on a usable surface of approximately 57,000 square meters.
The construction duration of the power plants, from the start of the works until its handing over, was on average about seven months. Moreover, solar power plants have a lifespan of about 25 years, and the recovery of the investment can be achieved in 4-7 years.
E.ON Energie Romania, a member of the German E.ON Group, is an integrated supplier of natural gas, electricity and energy solutions with a varied portfolio consisting of approximately 3.4 million clients, both residential ones, as well as companies and municipalities. The E.ON Group is one of the leaders of the energy market, having been present in Romania for 17 years. Since entering the local market, the company has invested around two billion euros, mainly in network modernization. At the same time, the value of the contributions transferred to the state and local budgets amounts to 2.7 billion euros.